2/13/08

Power tool storage cabinets

The last three weekends have not been as productive as I would have liked. I have been building power tool storage cabinets. The plans are from a magazine article and use 2X4's, pegboard and MDF. The frames are nicely done by rabbiting all the joints and glueing and screwing. The sides are Pegboard dado'd into the frame. The shelves are MDF. I'm makeing a specific place for every tool, and that is what's taking time and why I am not done yet. As you can see in the pic below, my circ saws sit on shelves with slots for the blade and guard. This allows them to rest on their bases nicely. The real casters should arrive this week. They temporarily sit on furnature dollies. My Delta Unisaw was the major tool used to make all the pieces, including ripping, rabbiting, and dado-ing.


I also visited Indy this last weekend to look at another auto lift I will buy. I wanted to see if it was built well enough and they had a showroom at their Indy dealer. It also gave me a day to hang out with my neices and their parent and grand parents. I decided that the lift is up to par and the price is right. I was going to order it this week, but realized that I need to make space in my shop to assemble the lift. This means I have to finish a couple projects, namely the power tool cabinets, the assembly of my tractor, and get the John deer tractor fixed as it suddenly has decided to have an electrical problem and not start.

1/14/08

Cribbing Ponies


This weekend I managed to build my cribbing ponies. Cribbing ponies are little stool like saw horses used to support each end of a cribbing timber. With a parallel pair of cribbing timbers set up on the ponies, a multiple number of timbers are laid across the cribbing timbers to work on them, adding mortises and tennons. I didn't have time to build my two power tool cabinets, so look for those in an upcoming post next week or so.

1/6/08

Beech beams



Here's a quick pic of the Beech beams I got from Amish John in Southeast Indiana a few weeks ago. They are pretty beefy. Top two are 16 footers, the rest (14) are 12 footers.


This weekend I cut the parts for Timber Cribbing ponies(on my new 1953 Delta unisaw), which I plan to assemble during the next week. I also went and looked at a barn that I could potentially help dismantle in exchange for the beams, but the largest are only 6X6 and it's all pine. I don't think it's worth doing, given all I need to focus on, though I thought it was a really neat barn. Besides the Cribbing ponies, this week I am going to buy the materials and begin cutting the parts to build my power tool storage cabinet. Right now I have power tools laying all over my bench and on the floor. I can't stand it. All the new tools need a proper, organized home.







1/1/08

Got through the holidays..

Well the holidays were stressful with all that needed to be done. We prepared the family party for 41 people and it all went well. I ate too much! I got a cold right after Christmas day, probably from stress and physical fatigue. So I lost a few of my vacation days to laying on the couch. It was not cool as I already felt like crap from not being able to work in my shop for almost 2 months. It was just one thing after another... I changed jobs and visited relatives for a few days while between jobs. I had to start preparing for Thanksgiving a few weekends prior. I did go get the Indiana timbers one weekend. Then it was time to prepare to Christmas.


So, I'm finally recovered. I fixed the plumbing problems in the farm house finally- got rid of the odor in the hot water with a bleach treatment to the water heater and a good flush. I somehow got the water softener working again. I got the new(used) dishwasher installed, and took care of some other cleaning and putting away of things in the house, plus all the holiday reciept paperwork is done now.


The last two days I have worked in my shop. I jockeyed all the cars around and used the forklift to move my new(used) car storage lift into the shop and I mounted the caster kit I bought on ebay. It took half a day to install plus finish reassembling and prepping the lift. One pulley needed to be removed and cleaned/blasted/lubed and reassembled. Well here's my lift with the cars stored. Now I need a second lift.

My next plans are:

1. Close in end of the barn/shop that used to be used for animals. Install overhead doors, and extend alarm system. This way I can store more in there.

2. Buy a second lift to make more shop space.

3. Finish assembling 1955 ford tractor restoration (4 days work?). and move it into the paint booth or into the end of barn.

4. Draw up timberframe plans for the shop and start to solidify dimensions. Find Illinois liscened Engineer that can stamp plans. Produce final prints and get stamped off.

12/7/07

What has happened so far?

Back in November or December of 2006 I became interested in timberframing. I don't know exactly how I came upon it, other than I was thinking about the new workshop I'd eventually build when I bought a property. Steve Chappell's "Timberframer's Workshop" was the first I bought. I ended up signing up for his intro timberframing workshop in June 2007 in Brownsfield, Maine. Being new to woodoodworking and beams/timbers, I tried to learn what I could online before the workshop. Being an avid ebayer I came across a bunch of beams for auction from a barn taken down near Rockford, IL. I won the auction and paid $0.26 a board foot(BD FT), which is how most wood is measured except for dimenisonal lumber. A board foot is the volume of 12X12X1 inch= 144cubic inches. My research had told me that red oak and pine were going for about $1.80 per BD FT rough sawn. So at the price I paid plus $440 to haul them to my place, it was still still under $0.40 per board foot. The beams are 8X8 and 8X10 pine. Three of them are 38ft long, and one is 24 feet long.
In early winter I came across some miscellaneous beams on ebay from a guy who owns an antique circular sawmill in Hebron, Indiana. Though I wasn't sure what I would do with them, they were a good price and I was learning. I bought a beautiful 12x12x 12 foot long knotty pine, some Hickory pieces and misc maple. I now knew someone with a saw mill that regularly sawed logs, including oak. The mill looked like a sawmill out of the turn of the century- it was!
At the same time I came across two doug fir beams 5.5X16 by 16 foot in Whiting, IN (ebay again). They had come out of an old bar, so I was told. I ended up paying $1.17/BD FT. That's not the greatest price, but doug fir is uncommon around here and by the time I de-nail and sand them, I'll still be under $1.80, the standard I'm using.


By February I came across 3 white oak beams 12 feet long near Indianapolis. Two are 10X10 and one is 12X12 . Since I was going there to visit relatives there anyway, it wasn't too much trouble to bring them back with me. Unloading was difficult though, with the beams weighing 750 lbs! I can't remember what I paid, but I'm sure it was under $0.60/BD FT. He also had a bunch of the slabs that were cut off the logs when cutting the beams. There were about 8 slabs, all 10" to 14" wide, 1.25 to 1.5 thick and some wane. I paid an extra $50 for the slabs. I didn't know what I was going to do with them. Later in the summer I ripped some of them to make bunk beds for a friends hunting cabin. I used the band saw chatter marks they had on them as character and highlighted them with stain.








I will definitly be able to use the oak timbers, though now sure where yet. I may have to have them resawn to a different cross section depending on the use. You can see what is called "checking" in the oak timbers above. Checking is a normal feature of large timbers. As a log or timber is cut green, as it dries, checks develop due to uneven drying. As the moisture escapes the timber, internal stresses develop which relieve themselves through checking. All timbers check, but hardwoods more than softwoods like pine. Oak, hickory, and hemlock seem to check the most. Checking is usually not considered a defect and does not compromise the integrity of a timber unless it is very severe - like greater than 3/4 inch and a check that runs completely thorugh a timber. Checking can be reduced by sealing the end grain of the green wood. The end grain are basically the capillaries of the tree and moisture will run out of the ends faster than the rest of the timber. If you seal the endgrain, it forces water to dry out the sides of the timber, which takes longer and is slower, thus allowing for more even drying and less checking.
My next venture was my timberframe class in Brownsfield, Maine. It was a wonderful class and even though I spent $1500 or so for the whole trip, the timber framing skills and general woodworking techniques I learned were well worth it. The class covered basic timberframe info, design styles, design of frames for loading and joint stress calculation, and had plenty of hands on experience. By the end of day 6, we erected our class project, a 2500 SQ FT home timberframe.










After the class I contracted with the sawmill guy to mill oak brace stock for me. Of the 66 pieces, most was red oak, but 15 were white oak. It was ok at $1/BD FT, but there were about 20 I had to return to him because they were even below grade 2. After having so many bad pieces in the lot and his giving me a hard time about replacing the bad ones, I no longer have much confidence in him to give me the grade I need. I've discovered that there are many hobby sawers in nearby Michigan who'd be happy to supply my brace stock in the future. I've been learning a lot about wood, sawing, drying, and controlling pests in wood from http://www.forestryforum.com/ The freshly sawn oak acually had some wood borer beetle larvae which eat holes in green wood. I sprayed with Sevin and it seemed to stop them cold. A few worm holes were made, but nothing to worry about structurally. Once the wood is dry, it's too hard for them to eat and then the wood is safe. The bad ones sticks the sawyer gave me are actually shown on top in the following picture. I did get these returned and replaced with proper grade stock.


In July, we had 4 straight days of heavy rains which softened the soil, and then a big windstorm came and blew over two 80 or so year old Spruce trees we had in the front yard at the farm. So I cut the branches and peeled the bark and put the trees in the barn for possible use in a timberframe later. The fresh sap caused mold to form on the logs in the barn after about 2 weeks. Following a suggestion from the forestryforum, I mixed a 10 percent bleach and water solution and sprayed down the logs. That took care of the mold! I learned that more than ten percent bleach will not be any more effective than 10 percent. A good tip to know.








In October I was going to visit relatives in Indy again, and I found some Beech beams to look at while down there. It was actually from an Amish gentleman near the Ohio border. I purchased 14 hardwood Beach beams 9X12 by 12 feet long and two that were 7X12 by 16 feet long. These are old growth beams from an old grainery barn. I got a good price of $700, plust it cost me $560 to move them. I will have these resawn probably to 7X12 or 8X12 which will cost another $500. In the end I figured these will cost $1.36/BD FT after sawing. It seems that if I can buy for about $0.60/BD FT, I can transport and resaw if needed and still keep costs well under $1.80 for substantial cost savings. I don't plan to use reclaim exclusively. When my design is finished, I will determine what of my existing reclaim can be used and now much new I'll have to order. I just got them hauled with Jason, the hauler from Woodstock, IL who I'd used to haul my on my first beam purchase. I accompanied him down to Indiana to get them and he was good company. He also hauled a used car lift I bought earlier in the week and delived it when he picked me up for the beam haul. Pics of that and the Beech beams in my next update.